Wind Farms in Weinviertel

82 wind turbines with a total capacity of 255.4 MW were installed almost simultaneously in Weinviertel by a wide variety of operators. In addition to the construction management of each individual wind farm, the requirements of the authorities as well as the interests of the operators had to be coordinated so that the building process could be optimized through cooperation.

EWS was primarily responsible and provided important services for the following wind farms (in alphabetical order):

Andlersdorf-Orth
Client: ImWind AO GmbH & Co KG, Wien Energie GmbH
Installed capacity: 13 WTG Enercon E-101, 39 MW
Start of operation: end of 2016
EWS service: construction management
 
Auersthal II
Client: WEB Windpark GmbH & Co OG
Installed capacity: 2 WTG Vestas V100, 4 MW
Start of operation: December 2015
EWS service: supportive construction management
 
Großkrut-Hauskirchen-Wilfersdorf
Client: ImWind GHW GmbH & Co KG, Windpark Rannersdorf II GmbH
Installed capacity: 12 WTG Senvion 3.2M114, 38.4 MW
Start of operation: spring 2016
EWS service: construction management
 
Gugelberg
Client: Gugelwind GesmbH
Installed capacity: 3 WTG Vestas V112, 9.9 MW
Start of operation: expected in the beginning of 2017
EWS services: planning and construction management
 
Hohenruppersdorf II
Client: smart-energy Betriebs-GmbH
Installed capacity: 10 WTG Vestas V126, 33 MW
Start of operation: December 2015
EWS services: planning and construction management
 
Ladendorf
Client: CE ImWind Ladendorf GmbH
Installed capacity: 6 WTG Enercon E-101, 18 MW
Start of operation: spring 2016
EWS Service: construction management
 
Marchfeld Mitte
Client: Windpark Marchfeld Mitte GmbH (WindLandKraft)
Installed capacity: 14 WTG Enercon E-101, 42 MW
Start of operation: spring 2015
EWS service: construction management
 
Paasdorf-Lanzendorf
Client: evn naturkraft Erzeugungsgesellschaft m.b.H., ImWind PL GmbH & Co KG
Installed capacity: 11 WTG Senvion 3.2M114, 35.2 MW
Start of operation: 2016/2017
EWS service: construction management
 
Parbasdorf II
Client: WEB Windpark GmbH & Co OG
Installed capacity: 4 WTG Vestas V112, 13.2 MW
Start of operation: spring 2016
EWS service: supportive construction management
 
Simonsfeld II
Client: Windpark Simonsfeld II GmbH
Installed capacity: 3 WTG Senvion 3.2M114, 9.5 MW
Start of operation: spring 2016
EWS services: planning and construction management
 
Spannberg II
Client: WEB Windpark GmbH & Co OG
Installed capacity: 4 WTG Vestas V112, 13.2 MW
Start of operation: December 2015
EWS service: supportive construction management

Special characteristics

  • 11 parallel projects – 82 wind turbines
  • Installed capacity of 255.40 MW
  • 8 wind farm owners (in alphabetical order: evn naturkraft, Gugelwind, ImWind, smart energy, WEB, Wien Energie, Windkraft Simonsfeld, WindLandKraft)
  • 3 different wind turbine manufacturers (Enercon, Senvion, Vestas)
  • 5 different wind turbine types
  • First-time erection of a Vestas V126 in Austria
  • Ecological construction management for approx. 50 MW
  • Construction of cable lines of a length of around 165 km
  • Shared cable routes in extremely confined space were implemented. Up to four cable systems including diverse conduits, grounding systems and warning bands were installed in part next to existing underground installations. This required continuous coordination with all parties involved (property owners, authorities, wind farm operators, construction companies) who carried out the work successfully according to EWS standards.
  • Coordination of shared transport routes for various wind farms in close cooperation with the building authorities
  • Coordination of the grid connection for various wind farms to a common cable route to the feed-in point

Challenge:

  • Parallel to Wind Farm Großkrut-Hauskirchen-Wilfersdorf is the ongoing large project „Autobahn A5“

The wind farm is separated from the Nordautobahn A5 in two parts. The construction phase of these two large-scale construction sites was simultaneous for the most part. Due to construction on the expansion of the autobahn, several access roads had to be changed or closed. This was particularly a challenge to the delivery of the large turbine components and the cranes. The wind turbine components could be delivered without any problems due to EWS active support in forming constructive cooperation between wind farm owners, the ARGE-Autobahn as well as the wind turbine manufacturers and deliverers.

 